description: "The system is pre-assembled and tested at Probot Systems. On-site installation typically takes one day with two people minimum. ⚠️ **Before You Begin** Read all safety instructions. Verify delivery against scope of delivery. Ensure site meets environmental conditions. All dimensions in…"
url: "https://www.probotsystems.com/docs/installation/"
updated: "2026-03-04"
---

# Installation

The system is pre-assembled and tested at Probot Systems. On-site installation typically takes one day with two people minimum.

⚠️ **Before You Begin**

Read all safety instructions. Verify delivery against scope of delivery. Ensure site meets environmental conditions. All dimensions in mm unless specified.

### Required Tools (Not Included)

- Forklift or pallet jack
- Level
- Metric socket set and wrenches
- Compressed air supply

### Site Preparation

- Verify level, solid concrete floor (min. 17 MPa / 2500 psi).
- Ensure adequate clearance per project layout.
- Verify electrical supply: 120/240 VAC dedicated circuit.
- Verify compressed air supply at required pressure/flow.
- Ensure network connectivity if remote monitoring is required.

### Uncrating and Positioning

- Inspect crate for damage before opening. Document any damage.
- Remove panels carefully. Keep all hardware and docs.
- Verify all items against the packing list.
- Lift the base with forklift using fork pockets.
- Position at installation location aligned with conveyor infeed.
- Lower base onto floor — check level.

### Electrical Connections

1. Verify main disconnect is OFF.
2. Connect power cable to control cabinet inlet.
3. Verify supply voltage matches cabinet nameplate.
4. Take the HMI tablet from the box inside the controler and plug it with identified cable.

### Pneumatic Connections

1. Connect air supply to system inlet.
2. Set regulator to operating pressure.
3. Check all fittings for leaks.
4. Verify FRL setup (if applicable).